Week By Week Tasks for Team Pathfinder
Week
Tasks
Notes

Week 1:
July 13-21

   
Week 2:
July 23-28
   
Week 3:
July 30-August 4
   
Week 4:
August 6-10
   
Week 5:
August 13-17
   
Week 6:
August 20-24
   
Week 7:
August 27-31
   
Week 8:
September 4-8
   
Week 9:
September 10-15
  • Complete Branding
  • Create Task list with owners
  • User scenarios
  • Create Work Site in DW4
  • Schedule meeting with FRH to discuss branding, content, sites
  • Update site map and add to work site

Get access to server

Include Dave in meeting schedule

Look at Chinese Newcomers site for method of managing large number of links

Week 10:
September 17-22
  • Feedback on comparative sites
  • Finalize comparative analysis
  • Feedback on Branding
  • Finalize branding
  • Start logo design
  • Content for F.C.P.S.
  • Functional Requirements Document
 
Week 11:
September 24-29
  • Review FRD with Client
  • Content for F.O.R.W.A.R.D. with FAQ
  • Finalize Site Map
  • Storyboards
  • Finalize Logo proposals
  • Review Logo with Client
 

Week 12:
October 1-6

  • Review and finalize Logo
  • First round of Design Comps
  • Content for X-Cell Club
  • Content for remaining text and links
  • Photographic Content
 
Week 13:
October 8-12
  • First Review of Designs
  • Update Designs
  • Style Guide
  • Functional Design Document
 
Week 14:
October 15-19
  • Second Design Review
  • Update Design
 

Week 15:
October 22-26

  • Final Site Comp approval
  • Design Templates
 
Week 16:
October 29-November 3
  • Build template for F.C.P.S.
  • Create Bug database
 
Week 17:
November 5-10
  • Alpha testing for F.C.P.S.
  • Templates for F.O.R.W.A.R.D.
  • Address open bugs
 
Week 18:
November 12-16
  • Alpha II testing
  • Resolve open bugs
 
Week 19:
November 19-21
  • Integrate remaining content into Templates
  • Complete Coding and Links
  • Browser testing
 
Week 20:
November 27-30
  • Beta testing
  • Resolve open bugs
  • Stage final site
 
Week 21:
December 3-7
  • Project Review
  • Maintenance Plan
  • Recommendations