Budget Proposal for Family
Restoration House Web Site |
|
|
|
|
30-Aug-01 |
|
Task |
Total Person Hours |
Resource* |
|
|
Select Agency |
4 |
T |
|
|
Branding and Target Audience Definition |
|
|
|
|
Define Site Goals |
8 |
T |
Combined hours of all team members |
|
Define Site Goals Completed |
0 |
|
|
|
Define Target Audience |
8 |
T |
Combined hours of all team members |
|
Define Target Audience Completed |
0 |
|
|
|
Feedback on Comparison Sites from FRH |
3 |
C |
|
|
Comparative Analysis |
5 |
C |
|
|
Branding |
15 |
T |
Combined hours of all team members |
|
Branding Completed |
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Planning |
|
|
|
|
Create MPP for FRH |
10 |
P |
|
|
Create Budget |
2 |
P |
|
|
Project Proposal |
15 |
T |
Combined hours of all team members |
|
Functional Requirements Document |
2 |
P |
|
|
Update FRD with Client Feedback |
2 |
P |
|
|
Technical Requirements Document |
4 |
I |
|
|
|
|
|
|
|
Work Site |
|
|
|
|
Create work site layout |
6 |
P |
|
|
Create and Maintain Journal (ongoing) |
20 |
P |
|
|
|
|
|
|
|
Content Acquisition |
|
|
|
|
Meet w/Agencies for Content Acquisition |
18 |
T |
Combined hours of all team members |
|
Create Content Chart |
2 |
P |
|
|
Agency Content Acquisition Completed |
0 |
|
|
|
|
|
|
|
|
Site Comps |
|
|
|
|
Create Home and secondary page comps |
50 |
T |
This represents total effort of each team member creating full comps. |
|
Site Comps Completed |
0 |
|
|
|
Create Logo for FRH |
12 |
D |
|
|
|
|
|
|
|
Info Architecture & Page Architecture |
|
|
|
|
Create Site Plan |
9 |
T |
Combined hours of all team members |
|
Create Site Map |
9 |
T |
Combined hours of all team members |
|
Get Approval on Site Map |
12 |
T |
Combined hours of all team members |
|
|
|
|
|
|
Styles |
|
|
|
|
Establish Styles in Detail |
8 |
C |
|
|
Styles Completed |
|
|
|
|
|
|
|
|
|
Content Creation |
|
|
|
|
Create Content |
80 |
I |
|
|
Content Completed |
|
|
|
|
|
|
|
|
|
Technical Engineering |
|
|
|
|
Create Functional Design Specification |
6 |
I |
|
|
Design Templates |
10 |
I |
|
|
Build Templates |
15 |
I |
|
|
Create Code & Links |
20 |
I |
|
|
Complete Coding & Links |
|
|
|
|
|
|
|
|
|
Testing |
|
|
|
|
Create bug database |
2 |
P |
|
|
Alpha Critique Session I |
6 |
T |
|
|
Resolve Alpha I bugs, update site |
12 |
I |
|
|
Alpha Critique Session II |
6 |
T+ |
Team plus Client |
|
Resolve Alpha Bugs and Changes |
12 |
I |
|
|
Cross browser testing |
4 |
I |
|
|
Beta Critique Session |
6 |
T++ |
Include clients, volunteers, team |
|
Resolve Beta bugs and Open Issues |
12 |
T |
|
|
|
|
|
|
|
Project Summary |
|
|
|
|
Submit Materials for Project Review |
12 |
T |
|
|
Establish content maintenance plan |
4 |
P |
|
|
Provide recommendations for future enh.ancements |
6 |
T |
|
|
Project Review |
24 |
T |
|
|
|
|
|
|
|
Total Person Hours |
461 |
|
|
|
Hourly rate |
$100 |
|
For this exercise, assume overall average hourly rate is $100/hour |
|
Total Budget |
$46,100 |
|
|
|
Proposal to Client w/15% buffer |
$53,015 |
|
|
|
|
|
|
|
|
|
|
|
|
|
*Resource Key |
|
|
|
|
D=Designer |
|
|
|
|
P=Producer |
|
|
|
|
I=Integrator |
|
|
|
|
Q=Quality Assurance |
|
|
|
|
C=Content Manager |
|
|
|
|
T=Entire Team |
|
|
|
|