| Budget Proposal for Family Restoration House Web Site | ||||
| 30-Aug-01 | ||||
| Task | Total Person Hours | Resource* | ||
| Select Agency | 4 | T | ||
| Branding and Target Audience Definition | ||||
| Define Site Goals | 8 | T | Combined hours of all team members | |
| Define Site Goals Completed | 0 | |||
| Define Target Audience | 8 | T | Combined hours of all team members | |
| Define Target Audience Completed | 0 | |||
| Feedback on Comparison Sites from FRH | 3 | C | ||
| Comparative Analysis | 5 | C | ||
| Branding | 15 | T | Combined hours of all team members | |
| Branding Completed | 0 | |||
| Project Planning | ||||
| Create MPP for FRH | 10 | P | ||
| Create Budget | 2 | P | ||
| Project Proposal | 15 | T | Combined hours of all team members | |
| Functional Requirements Document | 2 | P | ||
| Update FRD with Client Feedback | 2 | P | ||
| Technical Requirements Document | 4 | I | ||
| Work Site | ||||
| Create work site layout | 6 | P | ||
| Create and Maintain Journal (ongoing) | 20 | P | ||
| Content Acquisition | ||||
| Meet w/Agencies for Content Acquisition | 18 | T | Combined hours of all team members | |
| Create Content Chart | 2 | P | ||
| Agency Content Acquisition Completed | 0 | |||
| Site Comps | ||||
| Create Home and secondary page comps | 50 | T | This represents total effort of each team member creating full comps. | |
| Site Comps Completed | 0 | |||
| Create Logo for FRH | 12 | D | ||
| Info Architecture & Page Architecture | ||||
| Create Site Plan | 9 | T | Combined hours of all team members | |
| Create Site Map | 9 | T | Combined hours of all team members | |
| Get Approval on Site Map | 12 | T | Combined hours of all team members | |
| Styles | ||||
| Establish Styles in Detail | 8 | C | ||
| Styles Completed | ||||
| Content Creation | ||||
| Create Content | 80 | I | ||
| Content Completed | ||||
| Technical Engineering | ||||
| Create Functional Design Specification | 6 | I | ||
| Design Templates | 10 | I | ||
| Build Templates | 15 | I | ||
| Create Code & Links | 20 | I | ||
| Complete Coding & Links | ||||
| Testing | ||||
| Create bug database | 2 | P | ||
| Alpha Critique Session I | 6 | T | ||
| Resolve Alpha I bugs, update site | 12 | I | ||
| Alpha Critique Session II | 6 | T+ | Team plus Client | |
| Resolve Alpha Bugs and Changes | 12 | I | ||
| Cross browser testing | 4 | I | ||
| Beta Critique Session | 6 | T++ | Include clients, volunteers, team | |
| Resolve Beta bugs and Open Issues | 12 | T | ||
| Project Summary | ||||
| Submit Materials for Project Review | 12 | T | ||
| Establish content maintenance plan | 4 | P | ||
| Provide recommendations for future enh.ancements | 6 | T | ||
| Project Review | 24 | T | ||
| Total Person Hours | 461 | |||
| Hourly rate | $100 | For this exercise, assume overall average hourly rate is $100/hour | ||
| Total Budget | $46,100 | |||
| Proposal to Client w/15% buffer | $53,015 | |||